Project Map

Construction Activities
End of August 2007

Placing top soil behind the new sidewalks along Yelm Avenue West and Killion Road. The signal controller is scheduled to arrive on site and WSDOT will begin testing the controller in their lab. When the controller passes inspection the mast arms, signal heads, striping, and lights will be installed.